Pump Station Rehabilitation
Major Activities:
- Replacement of existing pumps, piping, motors, motor shafts, valves, VFDs, control panels, generator
- Demolition, removal, installation and modifications of existing concrete
- Addition of odor control system
Notable Specs:
Pump station will be bypassed during replacement of pumps and other construction activities. This force main that feeds the pump station is the main feed of the Nissan Plant located in Smyrna Tennessee.
Location: Smyrna, TN
Date Completed (Estimated): October 2024
Contract Value: $4,271,000.00
Owner: Town of Smyrna
Engineer: Thomas and Hutton