J. Cumby Construction was contracted by the North West Utility District to upgrade and expand their water treatment facility. The primary project scope was the construction of a six thousand square foot PALL membrane treatment facility as well as the rehabilitation of the sedimentation basin and backwash lagoons. Other work also included was interior and underground process piping and valves, Electrical, controls, and mechanical systems, paved access roads, miscellaneous new and upgraded appurtenances, a metal building, underground chambers, as well as general site work, fences, and gates. Once completed, the project increased the facility’s processing capacity by four million gallons per day.
Project Specs:
Location: Soddy Daisy, TN
Completion Date: July 2020
$8,200,000+ Contract Value