J. Cumby will be upgrading an existing wastewater treatment plant that currently treats 0.9 million gallons of wastewater per day.

Major Activities:

  • Expanding the existing facility’s control building by 2,310 sf

  • This includes an addition of (3) rooms:

-Chemical Feed – Currently in a separate building that will be demolished during this project

-Electrical & Control Room – Moving existing MCC & controls from a different area of the existing control building

-Open space

  • Renovations and additions to the facilities electrical services

  • Generator, motor control center, lighting, wiring

  • Demolition and removal of (2) existing sequencing batch reactor (SBR) systems

  • Installation of (2) new SBR systems

  • Blowers, decanters, analyzers, air supply lines, valves, connectors, pumps and instrumentation

  • Installation of new and modification of existing yard piping

  • Additional structural activities

  • New walkway canopy for the control building

  • Construction of a new structural steel canopy for the new blowers

PROJECT INFORMATION

  • Location: Morrison, TN

  • Date Completed (Estimated): December, 2023 

  • Contract Value of $3,863,859.77

  • Owner: West Warren-Viola Utility District  

  • Engineer: James C. Hailey & Company  

NOTABLE SPECS

  • Because this is a renovation to an operating facility, one of the two SBR basins must remain in service throughout construction. Sequencing of the equipment installation will require a staggered installation for each of the basins, rather than concurrent installation typical to new construction.